Project complexities, simplified by Alpha:
- Working within a large operational car production plant, requiring careful sequencing and logistics planning to maintain safe access and avoid disruption to manufacturing operations.
- Delivering a high-quality, dust-free concrete finish, requiring strict quality control and workmanship to meet operational and storage requirements.
- Designing a slab for temporary infrastructure with long-term use, ensuring durability and performance under continued HGV loading beyond the initial requirement.
- Integrating new drainage systems with existing infrastructure, ensuring effective performance without impacting ongoing site operations.
Scope of Works:
- Breaking out existing hardstandings and roadways, preparing the site for new construction works.
- Installation of new drainage systems, including connections into the existing site infrastructure to ensure effective surface water management.
- Construction of a large reinforced concrete slab, delivered as a continuous pour with edge thickenings to provide long-term structural performance.
- Achieving a high-quality, dust-free finish, suitable for sensitive materials storage and operational requirements.
- Design and construction to accommodate HGV loading, ensuring the slab remained suitable for heavy-duty use beyond the temporary structure lifespan.
- Construction of access ramps, footpaths and associated external works, enabling safe and efficient site operations.